STEP BY STEP THE RENOVATION OF YAKIMA CENTRAL LIBRARY |
|||
|
|||
| June 30, 2009 | Board members investigate the condition of Yakima Cental Library building | Phase I | |
| August 17, 2009 | Trustees and administrators meet to discern and prioritize needed changes | Phase I | |
| August 25, 2009 | Trustees authorize upgrading the HVAC system at Yakima Central | Phase I | |
| October 27, 2009 | Building a timeline - what needs to be done and in what order | Phase I | |
| February 23, 2010 | Auditorium space planning | Phase II | |
| May 25, 2010 | Heating and air conditioning replacement plan | Phase I | |
| May 25, 2010 | Resolution #10-005 Authorizing contract award for emergency HVAC renovation | Phase I | |
| May 25, 2010 | Planning for the future | Phase I | |
| June 29, 2010 | Replacing the HVAC system is well underway | Phase I | |
| July 27, 2010 | Progress report on HVAC renovation | Phase I | |
| August 24, 2010 | HVAC replacement on schedule and under budget | Phase I | |
| September 28, 2010 | Contractor conducting HVAC tests | Phase I | |
| September 28, 2010 | Trustees and Director Hixson discuss space configuration options for the new layout | Phase II | |
| October 26, 2010 | Board members inspect installed HVAC equipment with Director Hixson and Deputy Director McCracken | Phase I | |
| October 26, 2010 | Traffic flow study to understand how interior spaces are used | Phase III | |
| January 24, 2011 | Relocating public restrooms a top priority | Phase III | |
| March 28, 2011 | Contractor selected for Yakima Central Auditorium Conversion to office space | Phase II | |
| March 28, 2011 | HVAC renovation results in savings | Phase I | |
| April 25, 2011 | Auditorium renovation on schedule | Phase II | |
| May 23, 2011 | Budget and priorities set for renovation of the main floor of Yakima Central Library | Phase III | |
| May 23, 2011 | Accounting department moves into the new office space | Phase II | |
| July 25, 2011 | Trustees authorize a comprehensive study of the wiring capacity of the building for planning purposes | Phase III | |
| July 25, 2011 | Completion of HVAC system results in rebate from Pacific Power | Phase I | |
| August 22, 2011 | Architects offer library layout design options | Phase III | |
| September 25, 2011 | Remodel design in final phase of approval | Phase III | |
| October 24, 2011 | Director Hixson reports on the growing need to relocate the public restrooms. | Phase III | |
| November 14, 2011 | Plans to provide library services during construction | Phase III | |
| December 19, 2011 | Main library to be closed during the renovation | Phase III | |
| January 5, 2012 | Construction begins on Yakima Central renovation | Phase III | |
| January 23, 2012 | Staff work hard, weeding and moving the collection | Phase III | |
| February 28, 2012 | Director Hixson commends public service staff for their excellent work during the renovation process | Phase III | |
| March 26, 2012 | More power required for expanded computer plaza | Phase III | |
| April 23, 2012 | Board members and administrators review layout and furnishings of computer plaza | Phase III | |
| April 23, 2012 | Change orders approved | Phase III | |
| May 15, 2012 | Moving into the newly renovated library | Phase III | |
| May 16, 2012 | News announcement of library closure | Phase III | |
| May 19, 2012 | Downtown library set to reopen Monday | Phase III | |
| May 21, 2012 | Pictures of the completed remodeled Yakima Central Library | Phase III | |